LSB Parking Garage Closure -
LSB Parking Structure – Contractor Schedule
The attached flyer will be in the Y news on Monday 29 June 2026. The contractor will begin work in the LSB Parking Structure beginning on Monday 29 June 2026 and will continue work in the parking structure throughout the week at different floor levels and the contractor will be finished with his work on Saturday 4 July 2026. The LSB parking structure will reopen for parking on Monday 6 July 2026.
The contractor will be doing the following:
* Shotblasting the existing concrete parking surface
* Application of a new sealer on the existing concrete
* BYU Paint Shop to repaint the parking stalls.
Brian L. Johnson
Life Sciences Facilities Manager
College of Life Sciences
Brigham Young University
1100A LSB
Provo, Utah 84602
801-422-5683
brian_johnson(a)byu.edu<mailto:brian_johnson@byu.edu>